Henan Luoyang revealed houses was of poor quality: all-paper doors

Henan Luoyang revealed houses was of poor quality: all paper placed | | quality | wall _ news

According to Xinhua as the province's first high-rise houses of villagers, placed Yi Bin Zone of Luoyang City, Henan province zhugezhen village Kang first District of three combined demolition because of quality problems, by netizens exposed.


Disgruntled villagers posted online, "said ground crack, walling off ash, have paved the floor tiles of kitchens, bathrooms and waterproof to redo, every home is the exclusive paper doors, at least 20,000, this is the date? ”


Incident light, will investigate the building materials according to local official sources and inspection procedures.


  Inhabitants: cracked ground, walling off ash


It is understood that Kang placed first, Yi Bin zhugezhen Zhuge village community located in Luoyang City, covers an area of 405 hectares, a total of 49-building high-rise residential, total construction area of 650,000 square meters, was completed in August 2013. Beginning in November 2013 to 2014, began to focus on staying before the Spring Festival, up to now, community rehouse the villagers amounted to 1852, 10505.


Journalists interview found on the ground, has 49 18-storey high-rise building in the neighborhood, plenty of room for the plywood door is too thin, basic paper to fill in, can't even see the water, villagers have dubbed "paper solution" and the individual buildings inside the walls of cement missing, children can touch a crash out of the pit.


"Decoration, tile saws, construction of said that doors are too thin, and it was full of paper, saw the following border are afraid to kick bad, fear of blisters", 49th, Zhao Suiying said of the building, but the top sawed the door. Reporters saw the door top, pull out door plates filled brown paper, two layers of plywood can be break even by hand.


On the 11th floor of Ma Jianwei, others after the first snow wall leakage occurs in a living-room, balcony. Decorating outside knocking on walls when a thin layer of cement, Ma Jianwei found, since there is no cement, sand wall actually fell.


 Quality supervision station: only oversee acceptance procedures


According to the community building command long Ma Fang introduced, it was delivered has passed before final acceptance of the community.


Now that you have successfully passed acceptance check, why is exposed by villagers after the arrival of such a large number of quality problems? Is responsible for the construction of Luoyang City, 11th floor, Guang-Xin Liu Guoyong construction group, the project manager said, "wall added sand is due to workers in construction ' mortar Po ' too much. ”


It was responsible for building the Guangxin group Henan huaxing construction project quality supervision of construction supervision company described Chen Zhanxiu, head, "mortar treasure" is a mortar additives will save cement consumption, excessive added could cause a wall of sand, "had already found the problem, and ordered construction to rectify. ”


Works without rectification, acceptance without a why? Quality supervision station chief Zhang Tieliang Yanshi said, "we only oversee acceptance procedures, if the quality of participation is considered qualified, would be good. ”


After the incident, according to resettlement residential area where Yi Bin area management reform project of the preliminary determination, which was found during a return visit to housing quality problems, agreed upon with the consent of the people, home to replace or repair immediately, and strive to complete by the end of April. At the same time, Yi Bin will lead discipline inspection departments, courts and other departments involved in the establishment of joint investigation teams, investigation materials sources and inspection procedures. Yi Bin Wang Tao, Vice Secretary of the Working Committee of the party said the investigation found violations of violations, according to the law seriously.


(Original title: place "paper solution" kids touch out of wrestling pit)

(Edit: SN091)
02:39 on March 24, 2014 The Beijing News
(
河南洛阳一处安置房被曝质量差:清一色纸糊门|安置房|质量|墙体_新闻资讯

  据新华社电 作为全省首个村民高层安置房,安置河南省洛阳市伊滨区诸葛镇三个合并拆迁村庄的福民一号小区因质量问题,被网友曝光。


  有不满的村民在网上发帖称,“地面开裂、墙体掉灰,已经铺了地板砖的厨房、卫生间防水要重做,每家还都是清一色纸糊的门,至少2万个,这也算交工?”


  事件曝光后,当地官方称将调查建材进货渠道和检验手续。


  居民:地面开裂,墙体掉灰


  据了解,福民一号安置小区位于洛阳市伊滨区诸葛镇诸葛村,占地405亩,共建设49栋高层住宅,总建筑面积65万平方米,2013年8月完工。自2013年11月开始至2014年春节前开始陆续集中入住,截至目前,小区已安置村民共计1852户、10505人。


  记者实地采访发现,在这个拥有49栋18层以上高层楼房的小区内,许多房间的夹板门门板太薄,基本靠纸填,甚至不敢见水,被村民戏称“纸板门”;而个别楼房的墙体内不见水泥,小孩摔一跤都能碰出坑。


  “装修铺地砖要锯门,施工队说门板太薄,里面都是纸,锯了下面的边框怕踢坏,还怕被水泡”,49号楼房的赵遂英说,无奈之下把门的上边框锯了。记者从锯开的房门上端,掏出房门夹板中填充的牛皮纸,两层夹板甚至用手都可以掰断。


  在11号楼的马建伟家,交房后的首场雪,家里的客厅、阳台墙体就发生漏水。而装修时敲开墙体外一层薄薄的水泥,马建伟发现,由于没有水泥,墙体内的沙子居然都掉了下来。


  质监站:只对验收程序进行监督


  据小区建设指挥部指挥长马芳介绍,小区建成交付前已通过竣工验收。


  既然已经顺利通过验收,缘何在村民入住后又暴露出如此数量众多的质量问题?负责11号楼等工程建设的洛阳市广鑫建设集团有限公司项目经理刘国勇说,“墙体起沙主要是由于工人在施工中添加的‘砂浆宝’太多。”


  据负责广鑫建设集团项目工程质量监理的河南华兴建设监理有限公司负责人陈占修介绍,“砂浆宝”是一种砂浆添加剂,可节省水泥的使用量,过量添加可能造成墙体起沙现象,“当时已经发现问题,并责令建设单位整改了。”


  工程没有整改到位,缘何又通过了竣工验收?偃师市质监站站长张铁梁说,“我们只对验收的程序进行监督,如果参建各方认为质量合格,就可以。”


  事件发生后,按照安置小区所在的伊滨区管委会初步确定的整改方案,对于回访中发现的房屋质量问题,在征得群众同意后,立即入户更换或维修,力争4月底前完成。同时,伊滨区将成立纪检部门牵头、公检法等部门参与的联合调查小组,调查取证建材进货渠道和检验手续。伊滨区党工委副书记王涛表示,对于调查发现的违规违纪行为,将依法依规严肃处理。


(原标题:安置房“纸板门” 小孩摔跤碰出坑)


(编辑:SN091)