The author:(作者)归海一刀published in(发表于) 2014/5/27 9:14:25 CNOOC finished drilling 1th sea area near Xisha Island built in phases
May 27, according to the CNOOC official website news, operated by cosl management HYSY981 on May 27, successfully completing sea area near Xisha Island built in drilling operations for the first phase of its work, access to the relevant geological data. According to the customer's jobs plan previously, HYSY981 transitions on the same day, begin the second phase of its work.
The drilling began on May 2, is expected to end in mid-August.
(Original title: CNOOC completed sea area near Xisha Island built in first phase of drilling work)
中新网5月27日电 据中海油官方网站消息,由中海油服管理运营的HYSY981已于5月27日顺利完成西沙中建岛附近海域钻探作业第一阶段工作,获得了相关地质数据。按照客户此前制定的作业计划,HYSY981已于当日转场,开始第二阶段工作。
本次钻探作业从5月2日开始,预计8月中旬结束。
(原标题:中海油完成西沙中建岛附近海域钻探作业第一阶段工作)