Minxian County, Gansu province in response to victims 1 tent

1 tent the minxian County, Gansu province in response to victims: housing reconstruction was completed in October | | minxian County in Gansu province _ the earthquake news

Lanzhou, people's network, May 26 (reporter Cao Shulin) reporters learned from the minxian County, Gansu province the reconstruction Office, minxian County, you will arrange, push, make sure to follow the post-disaster reconstruction objectives of the master plan, completed by the end of October this year the victims house-building task so that affected families staying at our new House.


Minxian County in Gansu province Zhang County a 6.6-magnitude earthquake disaster reconstruction when there is substantial progress? Concern of the community, affected people are anxiously awaiting. The morning of 26th, people's daily, people's daily microBlog for publication of the minxian County, Gansu province visit the epicenter: nearly a year crowd still live in tents after the quake coverage. Reports, dingxi city of Gansu province and in minxian County party Committee and Government attaches great importance. That night, the minxian post-disaster reconstruction Office by calling a press conference, informed of housing reconstruction to the earthquake situation. According to the notification, all minxian earthquake victims housing reconstruction work will start construction in June as the full, completed in late October.


Informed that minxian County, according to the provinces overall deployment, higher level departments under the careful guidance, minxian County victims of building in accordance with the guiding principle of scientific co-ordination, classification, stubble, manpower planning construction, was pushed forward. Until now, the County's housing reconstruction 47268 households, has started construction 34766, starts 73.55%; shelter repair 35950, has started construction 25208, capacity utilization 70.12%.


Meichuan town village were farmers 469 households, tenants affected by redevelopment of 455 households has started 66, 14.5% per cent of tenants affected by redevelopment, the rest all tenants affected by redevelopment in June started construction. Yongguang village Club, four players, respectively, at the same time build 2 concentrated settlements, which placed masses 170 families. Current planning and design, ground leveling has been completed, some have started construction in June, fully operational.


Meichuan wing xingcun town there were farmers in 283 households, tenants affected by redevelopment 273 households, has started 20, 7.3% per cent of tenants affected by redevelopment, the rest all tenants affected by redevelopment in June started construction. While identifying build 1 concentrated settlements, which placed masses 190 families. Current planning and design, ground leveling has been completed, will start construction in June.


Bluegrass Pack Town Road and village there were farmers in 186 households, tenants affected by redevelopment of 150 households, has started 67, 44.7% per cent of tenants affected by redevelopment, the rest all tenants affected by redevelopment in June started construction. While identifying build 1 concentrated settlements, which placed masses of 60 households. The planning design and ground leveling has been completed, will start construction in June.


Informed that although around housing reconstruction did a lot of work and achieved some success, but part of the village, town, village, still has some difficulties and problems in the forward, there is a certain gap. Mainly because of the minxian County belongs to the quility, high above sea level in soil thawing late, especially rainfall in April, compared with same period last year to 54% this year, rainfall within 13 days of the month, is located in the mountainous area of Wing sing, yongguang, Lalu and other victims in the village of building progress have brought greater impact.


In accordance with the overall planning of post-disaster reconstruction objectives, in minxian County victims build tasks should be completed before the end of October, with conditions so that affected families staying at our new House. Minxian County, principal responsible comrades, "said provincial reconstruction planning requirements, which must be completed, to be completed. "According to the County's overall progress, minxian County, multiple measures simultaneously, strengthen the policy advocacy, according to time, inversion duration, to push to ensure completion of the annual task of reconstruction.


Minxian County, said the levels of compliance in order to ensure the quality of post-disaster reconstruction of minxian County, funds management, cadres and clean and rebuild, completed tasks, welcomes media supervision, and for their valuable views.

22:36 May 26, 2014 People's daily online
(
甘肃岷县回应灾民住1年帐篷:住房重建10月完工|地震|甘肃岷县_新闻资讯

  人民网兰州5月26日电 (记者 曹树林)记者从甘肃岷县灾后重建办公室获悉,岷县将多措并举、强力推进,确保按照灾后重建总体规划的目标要求,在今年10月底前完成灾民建房任务,使受灾户入住新居。


  甘肃岷县漳县6.6级地震灾后重建何时能有实质性进展?社会各界高度关注,受灾群众更是焦急等待。26日上午,人民网、人民日报官方微博刊发了《甘肃岷县震中回访:地震过后近一年 群众依旧住帐篷》的报道。报道引起甘肃省、定西市及岷县党委政府的高度重视。当晚,岷县灾后重建办公室致电记者,通报了地震灾区住房重建情况。根据通报,岷县地震灾区所有受灾群众住房重建工作将在6月份全面开工建设,10月底完工。


  通报称,岷县按照省市总体部署,在上级有关部门的精心指导下,岷县灾民建房按照科学统筹、分类指导的原则,压茬进行,统规自建,有序推进。截止目前,全县住房重建户47268户,已开工建设34766户,开工率73.55%;住房维修户35950户,已开工建设25208户,开工率70.12%。


  梅川镇永光村共有农户469户,其中重建户455户,已开工66户,占重建户的14.5%,其余重建户6月份全部开工建设。同时在永光村三社、四社分别建设2个集中安置点,安置群众170户。目前规划设计、场地平整已完成,部分已开工建设,6月份全面开工。


  梅川镇永星村共有农户283户,其中重建户273户,已开工20户,占重建户7.3%,其余重建户6月份全部开工建设。同时确定建设1个集中安置点,安置群众190户。目前规划设计、场地平整已完成,将于6月份开工建设。


  禾驮乡拉路村共有农户186户,其中重建户150户,已开工 67户,占重建户的44.7%,其余重建户6月份全部开工建设。同时确定建设1个集中安置点,安置群众60户。目前规划设计和场地平整已完成,将于6月份开工建设。


  通报称,虽然围绕住房重建做了大量工作,取得了一定成效,但部分乡、镇、村、社在推进工作中还有一定困难和问题,存在一定差距。主要是由于岷县属于高寒阴湿区,境内海拔高,土壤解冻迟,尤其是今年4月份降雨量较去年同期增长54%,月内降水13天,对地处山区的永星、永光、拉路等村的灾民建房进度带来了较大影响。


  按照灾后重建总体规划的目标要求,岷县应于10月底前完成灾民建房任务,具备入住条件,让受灾户入住新居。岷县主要负责同志表示,“按省上重建规划要求,这个目标必须完成,也能够完成。”根据全县总体进展,岷县正在多措并举,加强政策宣传,按照时间节点,倒排工期,强力推进,确保完成年度重建任务。


  岷县表示,为了确保岷县的灾后重建质量达标,资金管理规范,干部廉洁重建,按期完成任务,欢迎媒体监督,并提出宝贵意见。


2014年05月26日22:36
人民网
)