Hunan 1 bridge was built 6 years as cellular

English

中文

Hunan 1 bridge was built 6 years with honeycomb | | piers testing _ news
On October 15, 2016, the Zhangjiajie Cili County, Hunan province, Lishui River Bridge pile "scarred" as being "moth". Dongfang IC

Changsha, October 17 Reuters new media (reporters Bai Tiantian) recently, the media reported that Hunan Zhangjiajie Cili County a complete 6 years of Lishui River Bridge pile foundation concrete shed, exposure of reinforcing bars, similar to "honeycomb", questioned the existence of quality problems.


Cili County Government official told reporters, the relevant departments and bridge design, construction, supervision and had rushed to the scene to see 17th third-party authentication institutions at the provincial level have also entered the scene detection. After the inspection report, will be to maintain the bridge immediately, allows the public to rest assured. If you have safety problems, serious corrective action.


It is understood that the Cili County with the Chengguan hydropower station water repair in the near future, Li River water level reduces, city Lishui river bed exposed, Li River Bridge pile foundation of bridge piers part exposed. According to the pictures circulating on the Internet, appears at the bottom of piles of Pier concrete with different degrees of loss, part steel bars exposed.


Bridge design project leader given explanation is that Li River Bridge in bridge design was done at the beginning of a lot of investigation work, bridge design meets the design specifications, shedding occurs because may be related to other factors such as water.


Hunan province, a bridge expert analysis shows that there are multiple possible, construction of the first bridge might not be according to the design requirements, pile buried in the riverbed below one meter also is not fully considered in the design of diversion problem, rivers rush on bridge pier scour is serious. If for this reason, should be dealt with as soon as possible, such as pouring pile again and diversion measures.



Responsible editor: Wei chun





Article keywords:
Pier testing

I want feedback
Save a Web page
Xinhua
湖南1大桥建成6年形同蜂窝|桥墩|检测_新闻资讯
2016年10月15日,湖南省张家界市慈利县,澧水大桥桥墩桩基“伤痕累累”如遭“虫蛀”。 东方IC 图

  新华社长沙10月17日新媒体专电(记者白田田)近日,有媒体报道称,湖南张家界市慈利县一座建成6年的澧水大桥桩基外围混凝土脱落、钢筋外露,形同“蜂窝”,被质疑存在质量问题。


  慈利县政府有关负责人向记者表示,有关部门和大桥设计、施工、监理方已经赶往现场查看,17日省级第三方鉴定机构也已进入现场开始检测工作。检测报告出来后,将立即对大桥进行维护,让公众放心。如果有安全隐患问题,将认真进行整改。


  据了解,近期随着慈利县城关电站放水检修,澧水水位降低,城区段澧水河床裸露,澧水大桥的桥墩桩基部分显露出来。根据网上流传的图片,一些桥墩桩基底部出现了不同程度的混凝土脱落现象,部分钢筋暴露在外。


  桥梁设计方项目负责人给出的解释是,澧水大桥在桥梁设计之初就做了大量考察工作,桥体设计本身符合设计规范要求,出现脱落的原因可能与水流等其他因素有关。


  湖南省一位桥梁专家分析认为有多种可能,一是大桥施工时可能没有按设计要求,将桩基埋于河床以下一米;也可能是在设计时没有充分考虑导流问题,河水流速比较急,对桥墩冲刷严重。若是这种原因,应该尽快处理,比如重新浇筑桩基,并做好导流措施等。



责任编辑:隗俊