Survivors of Jiangxi power plant: more than 10 minutes of platform collapse

English

中文

Survivors of Jiangxi power plant: more than 10 minutes of platform collapse

Aerial working platform collapsed in fengcheng power plant

Rescue workers at the collapse site search clear

Rescue workers victims out of the scene of the accident

Phase III projects in Yichun city, Jiangxi fengcheng power plant cooling tower construction platform collapsed a particularly serious accidents occur. As of 24th, at 22 o'clock, confirmed the accident site 74 people were killed, 2 wounded. After the accident, was out of the country visiting General Secretary of the CPC Central Committee, State President, Chairman of the Central Military Commission, he immediately issued instructions, Jiangxi province, asked related departments organized rescue and treatment, disposal and rehabilitation work as soon as possible, identified profound lessons, serious accountability.


Politburo Standing Committee, the State Council, China's Prime Minister, Li keqiang instruction requires racing against time to save trapped people, going all out to treat the injured, do their utmost to minimize casualties. To prevent such accidents from happening again.


  Construction platform collapsed to 74 dead and 2 injured


On November 24 at about 7:40, Yichun, Jiangxi province, the third-phase expansion project in fengcheng power plant level d section cooling tower crane suddenly collapsed, causing the above template collapsed concrete channels. When the accident happened, construction units are zero points and an early handover. As of bei Qing press, reporters learned from the rescue headquarters, confirmed the accident site 74 people were killed, 2 wounded.


At present, the staff 68 victims have been checked to confirm identity. Confirm the status of the youngest victims of 23 years old, maximum 53 years old. Local governments are trying to do a good job reception, comfort to the families of the victims.


At 6 o'clock in the afternoon yesterday, Jiangxi province held in fengcheng power plant "11·24" Press Conference. Accident rescue headquarters commander, Vice Governor of Jiangxi province, Li Yihuang reported that cooling tower height of 145 meters of an accident, has completed construction at present more than 70 meters high. Conference, November 24 at 7:40, Yichun, Jiangxi province, the third-phase expansion project in fengcheng power plant level d section cooling tower crane collapsed, causing the above template collapsed concrete channels.


  About


  Survivors: more than 10 minutes of platform collapse


"I don't know what happened, after I run scared silly. "Journalists in fengcheng city people's Hospital to see the current treatment of survivors, Wang Yao-sheng. He was also at the scene, hospital care for several of his coworkers recalled the moment of panic.


24th just after 7 o'clock in the morning, they get to cooling tower, over more than 10 workers, are zero and the early handover. Above their heads more than 70 meters high, build a construction platform, there are also dozens of workers. About five minutes later, they suddenly heard a shout from above, then see the scaffolding fall, hit fallen water tower and secure channel. On the ground floor of workers ran outside into the cooling tower. Just more than 10 minutes of the period, the entire construction platform collapsed completely.


"When construction platform lifts, collapsed. In addition to coworkers in the surface layer, above all fall, steel material down below. "Wang Yao-Sheng said.


Wang Yaolong said of workers managed to escape from the ground floor, the ground floor workers to escape from every day but two people were slightly injured, mostly from Tianshui city, Gansu province.


According to a witness at the scene said the collapsed rink construction platform height of at least 20 stories high.


  Rescue


  Jiangxi Fire Corps mobilized unmanned rescue


According to armed police fire brigade group Commander of Jiangxi Fang Lingchun introduced, Fire Department launched a trans-regional emergency reinforcement plan, a one-time mobilization of Yichun, Nanchang, Xinyu, JI an attendance of four fire brigade and corps command a total of 277 in the fire services officers and men, 43 fire duty cars, 10 fire search and rescue dogs and life detectors, 12 2 fire-fighting drones to participate in the rescue.


Public information, the accident power plant is located in the stone village West of fengcheng city of Tonggu mountain, site 8 kilometers away from fengcheng, about 60 kilometers from Nanchang, about 0.5 km south of the ganjiang River, East of Highway about 0.6 km, 2.8 km south of fengcheng cement plant.


Jiangxi province, Jiangxi fengcheng power plant by investment company, China guodian group at 55%, 45% stakes to form a limited liability corporation. Jiangxi fengcheng power plant, the third-phase expansion project funded by the Jiangxi company building, is the focus of Jiangxi electric power construction project.


In last night's press conference, the local reported that phase III expansion project started on December 28, 2015 in fengcheng power plant, cooling tower projects started in April this year.


  Casualties are from Hebei billion to companies


According to reports, the Hebei billion to smoke Tower engineering, Ltd is specializing in cooling towers, chimneys, environmental engineering construction and project of a company.


Cooling tower and chimney construction project engineering department engineer Liao Huishou said, is hyperbolic cooling tower construction, buildings belonging to the complex type. Cooling tower and thin wall construction platforms follow construction progress uplift. When accidents occur, cooling towers have been building to more than 70 meters.


Green newspaper reporter querying business and information found in the North, Hebei billion to smoke Tower engineering limited company registered on October 29, 2003, with registered capital of 100 million Yuan. Its business scope, including smoke Tower engineering, cooling tower material sales. North Green newspaper reporter called them several times yesterday Zhang Yunping, Chairman of the company, but the display is powered off, the company was still unanswered.


All the casualties in the accident were from the company, some workers from the Cheng ' an County, Hebei, killed workers focused on Cheng ' an County, Hebei province, Li Tuan town white fan Tuan, both Tuan village. After the accident, Cheng ' an already established two emergency accident disposal Department rushed to the scene disposal follow-up Cheng ' an is also urgent statistical details of the dead and injured workers on the ground.


Public information, Hebei billion times to get owners and outstanding contractor's certificate issued by the competent, quality certificates and other honors. In July this year, Hebei billion to tobacco company holds the trademark "billion to smoke Tower" was identified as a famous brand of Hebei. In addition, the companies of 8500 square meters in Hebei guohua Dingzhou power plant cooling towers, 8500 square meters of Henan qinbei power plant cooling towers that the domestic construction industry quality highest honor "Luban Prize".


However, public information, billion to tobacco Tower engineering company, Hebei construction projects in recent years have occurred several worker deaths and injuries from accidents.


On June 8, 2012, China energy group-owned subcontractor of Hunan provincial thermal power construction company, Hebei billion to smoke Tower engineering company in weixin, Yunnan coal and power integration projects in the construction of cooling towers, scaffold collapse, caused the death of 7 people fall.


May 23, 2011, Shandong Chiping County, a power plant under construction accident, according to the Department, Chiping Hao Ji power station construction site projects undertaken by Hebei billion to smoke Tower engineering, Ltd, steel tube air leak accident occurred at 9:30 A.M. on the day, resulting in 5 construction workers injured, 1 worker injuries died.


April 14, 2009, is located in Nansha district huangge second stage cooling tower of power plant construction site in Nansha of Guangzhou, Hebei billion to smoke co building contractors, in the cooling tower construction site, due to the car in the back during a collision to a platform column, leading to collapse of the platform, platform worker Zhang, Liu, 2 people were killed the down platform, 1 additional worker was injured.


Edition/reporter Li Tiezhu sails, Xinhua and CCTV


Photo/Xinhua News Agency


(Editors: Biao Guo UN832)
2016-11-25 04:35:06
The Beijing Youth daily
江西电厂事故幸存者:十几分钟平台全坍塌

航拍丰城电厂施工平台倒塌事故现场

救援人员在倒塌现场搜寻清理

救援人员将遇难者送出事故现场

  江西宜春市丰城发电厂三期在建项目发生冷却塔施工平台坍塌特别重大事故。截至24日22时,确认事故现场74人死亡,2人受伤。事故发生后,正在国外访问的中共中央总书记、国家主席、中央军委主席习近平立即作出重要指示,要求江西省和有关部门组织力量做好救援救治、善后处置等工作,尽快查明原因,深刻汲取教训,严肃追究责任。


  中共中央政治局常委、中国国务院总理李克强作出批示,要求争分夺秒抢救被困人员,全力以赴救治伤员,尽最大努力减少伤亡。防止此类重特大事故再次发生。


  事发 施工平台倒塌 致74死2伤


  11月24日7点40分左右,江西省宜春丰城电厂三期扩建工程D标段冷却塔平桥吊突然发生倒塌,造成上面模板混凝土通道坍塌。事故发生时,施工单位正在进行零点班和早班交接。截至北青报记者发稿,记者从现场救援指挥部获悉,确认事故现场74人死亡,2人受伤。


  目前,工作人员已核对确认了68名遇难者身份信息。确认身份的遇难者年龄最小的23岁,最大的53岁。当地政府正在全力做好遇难者家属接待、安抚工作。


  昨天下午6点,江西省召开丰城电厂“11·24”事故新闻发布会。事故救援指挥部总指挥长、江西省副省长李贻煌通报称,发生事故的冷却塔高度145米,目前已施工完成70多米高。发布会称,11月24日7时40分许,江西省宜春丰城电厂三期扩建工程D标段冷却塔平桥吊倒塌,造成上面模板混凝土通道坍塌。


  讲述


  幸存者:十几分钟平台全坍塌


  “不知道发生了什么,我逃出来以后就吓傻了。”记者在丰城市人民医院见到了目前在接受治疗的事故幸存者王摇胜。他和当时也在现场、现在医院照顾他的几名工友回忆了那惊恐的一刻。


  24日一早刚过7时,他们10多位工友就到达冷却塔内,进行零班与早班的交接。在他们头顶上方70多米的高处,搭建有施工平台,那里还有几十名工人。大概五分钟后,他们突然听到头顶上方有人大声喊叫,接着就看见上面的脚手架往下坠落,砸塌水塔和安全通道。在地面层工作的工人迅速往冷却塔外跑。短短十几分钟的时间内,整个施工平台完全坍塌下来。


  “当时上下施工平台用的电梯,一起坍塌了。除了地面层的工友,在上面的人全部坠落,被钢筋等材料压在下面。”王摇胜说。


  从地面层成功逃生的工人王耀龙说,地面层的工人除了两人轻伤外都安全逃生,他们主要来自甘肃天水市。


  据现场目击者称,坍塌施工平台目测高度至少20层楼高。


  救援


  江西消防总队调集无人机救援


  据武警江西消防总队总队长房凌春介绍,消防部门启动了跨区域应急救援增援预案,一次性调集宜春、南昌、新余、吉安四个消防支队以及总队全勤指挥部共277名消防指战员、43辆消防执勤车、10条消防搜救犬、12台生命探测仪、2架消防无人机参加现场救援。


  公开资料显示,此次发生事故的电厂位于丰城市西面石上村铜鼓山,厂区距丰城市区8公里,距南昌市约60公里,南临赣江约0.5公里,东距丰高公路约0.6公里,北距丰城水泥厂2.8公里。


  江西丰城电厂是由江西省投资公司、中国国电集团分别按55%、45%股份比例组建的有限责任公司。江西丰城电厂三期扩建工程由江西赣能股份有限公司出资建设,是江西省电力建设重点工程。


  在昨天晚上的新闻发布会上,当地通报称,丰城电厂三期扩建工程2015年12月28日开工,其中冷却塔项目今年4月开工。


  伤亡人员均来自河北亿能公司


  据介绍,河北亿能烟塔工程有限公司是专业从事冷却塔、烟囱、环保工程建设施工及项目改造的一家公司。


  冷却塔与烟囱施工项目的工程部工程师廖辉寿介绍说,冷却塔是双曲线建设工程,属于复杂的建筑种类。冷却塔外壁薄,施工平台跟随施工进度抬升。发生事故时,冷却塔已建设到70多米。


  北青报记者查询工商信息发现,河北亿能烟塔工程有限公司注册于2003年10月29日,注册资本1亿元人民币。其经营范围包括烟塔工程、冷却塔材料销售等。昨天北青报记者多次致电该公司董事长张运平,但显示已关机,该公司电话也始终无人接听。


  此次事故中所有伤亡人员均来自该公司,部分工人来自河北成安县,死亡工人集中在河北省成安县李家疃镇白范疃村、抹疃村这两个村。事故发生之后,成安县已经紧急成立两个事故处置部,奔赴现场处置后续工作,成安县当地也正在紧急统计死伤工人的详细情况。


  公开资料显示,河北亿能多次获得业主和主管部门颁发的《优秀承包商证书》、《优质工程证书》等荣誉。今年7月,河北亿能烟塔公司持有的商标“亿能烟塔”被认定为河北著名商标。此外,该公司承建的河北国华定州电厂8500平米冷却塔、河南沁北电厂8500平米冷却塔工程获得国内建筑行业工程质量最高荣誉奖“鲁班奖”。


  但是,公开资料显示,河北亿能烟塔工程公司承建的项目近年也曾发生过数起工人死伤的安全事故。


  2012年6月8日,中国能源建设集团所属湖南火电建设公司分包单位河北亿能烟塔工程公司在云南威信县煤电一体化项目冷却塔施工中,脚手架坍塌,造成7人坠落死亡。


  2011年5月23日,山东茌平县一在建电厂突发事故,据有关部门通报,茌平郝集电厂建设工地工程由河北亿能烟塔工程有限公司承建,当天上午9点半发生钢内筒气囊漏气事故,造成5名施工人员受伤,1名工人因伤势过重抢救无效死亡。


  2009年4月14日,位于南沙区广州南沙黄阁热电厂二期冷却塔建设工地,由河北亿能烟塔有限公司承建,在冷却塔施工现场,由于汽车吊在后退过程中碰撞到一作业平台的支撑柱,导致该作业平台倒塌,平台上工人张某、刘某2人被倒下平台砸死,另1名工人受伤。


  本版文/本报记者 李铁柱 张帆 新华社 央视


  供图/新华社


(责任编辑:郭彪 UN832)